How Long Does Delivery and Installation Take for a Carousel Ride?
When purchasing a carousel ride for your amusement park, one of the most important questions is: how long will delivery and installation take? Understanding the timeline helps park operators plan openings, marketing, and investment schedules more effectively.
This article will guide you through the typical delivery process, installation steps, and factors that can affect the overall timeline.

1. Production Time of a Carousel Ride
The first stage is manufacturing. At HOTFUN, we only sell brand-new carousels (no second-hand or rentals). Depending on the size and customization level:
- Mini carousel (3–8 seats): 15–25 days
- Medium carousel (12–24 seats): 25–40 days
- Large or double-deck carousel: 45–60 days
- Fully customized themed carousel: 60–90 days
👉 Tip: Ordering in off-peak seasons may shorten production time.
2. Shipping and Delivery Time
Shipping depends heavily on the buyer’s location. Carousels are usually transported in 20ft or 40ft containers.
- Southeast Asia: 7–15 days
- Middle East: 20–30 days
- Europe: 25–35 days
- Africa: 30–40 days
- South America: 35–45 days
On average, shipping adds 2–6 weeks to the timeline.
3. Installation Time
Once the carousel arrives at the site, installation begins. HOTFUN provides professional engineers for overseas installation or remote guidance. Typical installation times are:
- Mini carousel: 2–3 days
- Medium carousel: 5–7 days
- Large or double-deck carousel: 10–15 days
This includes assembly, electrical setup, testing, and safety inspection.
4. Factors That Affect the Timeline
Several elements can influence delivery and installation:
- Customization level – Unique themes and designs require more production time.
- Shipping season – Global freight rates and transit times may fluctuate.
- Customs clearance – Documentation and local inspections can cause delays.
- Site preparation – Foundation and electrical work should be completed before installation.
5. HOTFUN’s Advantage
As a global carousel ride manufacturer, HOTFUN ensures a smooth and predictable delivery process:
- ✅ Strict production schedule with real-time updates
- ✅ Professional packing and logistics support
- ✅ Overseas installation team or video guidance
- ✅ After-sales service and warranty included
Conclusion
From production to installation, the total timeline for a carousel ride usually ranges from 6–12 weeks, depending on size, customization, and shipping distance. By planning early and working with a reliable manufacturer like HOTFUN, park operators can launch their attractions on time and avoid unnecessary delays.
Related recommendations
-
What Models of Carousel Amusement Facilities Are Available?
103Discover the different carousel ride models for amusement parks and indoor centers. From mini carousels to luxury double-decker designs, HOTFUN provides certified and customizable options.
View details -
Professional Ferris Wheel Supplier (HOTFUN)| High-quality Ferris Wheel Customization and Installation Solutions
285Professional Ferris wheel supplier, providing one-stop services including Ferris wheel design, custom manufacturing, installation and maintenance, suitable for cultural tourism projects, city landmarks, theme parks. Support global export, safe and...
View details -
Maintenance and Care Requirements for Bumper Cars in Amusement Parks
690Bumper cars are one of the most popular and exciting attractions in amusement parks around the world. While they are designed to be safe and durable, proper maintenance and regular inspections are essential to ensure they operate smoothly, safely...
View details -
How do we choose the right amusement equipment?
1554Choosing the right rides is one of the important steps in building a theme park or amusement park. Here are some considerations to help you choose the right ride: Target Audience: Determine what age group your primary target audience is, su...
View details
chinaparkrides





Leave a Reply