How Long Does Delivery and Installation Take for a Carousel Ride?
When purchasing a carousel ride for your amusement park, one of the most important questions is: how long will delivery and installation take? Understanding the timeline helps park operators plan openings, marketing, and investment schedules more effectively.
This article will guide you through the typical delivery process, installation steps, and factors that can affect the overall timeline.

1. Production Time of a Carousel Ride
The first stage is manufacturing. At HOTFUN, we only sell brand-new carousels (no second-hand or rentals). Depending on the size and customization level:
- Mini carousel (3–8 seats): 15–25 days
- Medium carousel (12–24 seats): 25–40 days
- Large or double-deck carousel: 45–60 days
- Fully customized themed carousel: 60–90 days
👉 Tip: Ordering in off-peak seasons may shorten production time.
2. Shipping and Delivery Time
Shipping depends heavily on the buyer’s location. Carousels are usually transported in 20ft or 40ft containers.
- Southeast Asia: 7–15 days
- Middle East: 20–30 days
- Europe: 25–35 days
- Africa: 30–40 days
- South America: 35–45 days
On average, shipping adds 2–6 weeks to the timeline.
3. Installation Time
Once the carousel arrives at the site, installation begins. HOTFUN provides professional engineers for overseas installation or remote guidance. Typical installation times are:
- Mini carousel: 2–3 days
- Medium carousel: 5–7 days
- Large or double-deck carousel: 10–15 days
This includes assembly, electrical setup, testing, and safety inspection.
4. Factors That Affect the Timeline
Several elements can influence delivery and installation:
- Customization level – Unique themes and designs require more production time.
- Shipping season – Global freight rates and transit times may fluctuate.
- Customs clearance – Documentation and local inspections can cause delays.
- Site preparation – Foundation and electrical work should be completed before installation.
5. HOTFUN’s Advantage
As a global carousel ride manufacturer, HOTFUN ensures a smooth and predictable delivery process:
- ✅ Strict production schedule with real-time updates
- ✅ Professional packing and logistics support
- ✅ Overseas installation team or video guidance
- ✅ After-sales service and warranty included
Conclusion
From production to installation, the total timeline for a carousel ride usually ranges from 6–12 weeks, depending on size, customization, and shipping distance. By planning early and working with a reliable manufacturer like HOTFUN, park operators can launch their attractions on time and avoid unnecessary delays.
Related recommendations
-
How to Choose the Right Amusement Rides for Your Theme Park
249Discover how to choose the right amusement rides for your theme park. Learn key factors like safety, ride variety, supplier credibility, maintenance, and ROI to attract more visitors and maximize your investment.
View details -
Pirate Ship Chain and Cable Maintenance: Extending Service Life
183Learn how to maintain pirate ship chains and cables to extend service life. Daily, weekly, and annual maintenance tips to ensure safety, durability, and lower repair costs.
View details -
Battery vs Ground-Net Bumper Cars: Which Is Safer and More Profitable?
197Compare battery vs ground-net bumper cars to find the safest and most profitable option for your amusement park. Learn about costs, maintenance, and best use cases.
View details -
What Safety Certifications Are Required for Amusement Rides in Europe?
197Discover the key safety certifications required for amusement rides in Europe, including EN 13814, CE marking, and TÜV inspections. Learn what buyers and park operators must know to ensure compliance, smooth import, and safe operation.
View details
chinaparkrides





Leave a Reply